26 Ebury Bridge Road, Rights of Light (RoL) Payment Settlement

Decision Maker: Executive Director of Regeneration, Economy and Planning

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Decision Taken: The Executive Director of Regeneration, Economy & Planning has approved the settlement of a Rights of Light claim relating to Flat A, 1 Ebury Bridge Road, and authorised the Council to enter into a Deed of Release in exchange for compensation, securing the release of third-party rights and supporting the continued delivery of Phase 2 of the Ebury Bridge Estate Renewal project while mitigating the risk of legal challenge, injunction proceedings and associated programme impacts.

 

Publication date: 13/07/2026