Ebury Phase 2 - Westminster Housing Development Limited (WHDL) - Novations of Main Works Contractor and Professional Consultants

Decision Maker: Executive Director of Regeneration, Economy and Planning

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Decision Taken: The Executive Director of Regeneration, Economy & Planning has approved the novation of the Ebury Phase 2 main works contract, professional consultant appointments and associated parent company guarantee from Westminster City Council to Westminster Housing Developments Limited (WHDL), together with the entry into post-novation warranties, to enable WHDL to assume responsibility for delivery of the development.

 

Publication date: 13/10/2026

Date of decision: 29/09/2026

Accompanying Documents: