Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To approvethat the Oxford Street Scheme proceed to Stage 3, detail design, as part of the Oxford Street Programme.
Cabinet approved the option to proceed to Stage 3 design on the basis set out in the report in the knowledge that the remaining funding is yet to be formally confirmed.
Cabinet also approved spend of £3.845m to progress the Stage 3 design.
Reasons for Decision: The Stage 2 design for Oxford Street is complete and the finalisation of design is required in advance of pre-mobilisation and construction. A decision is required on how to progress the Oxford Street project.
Implementation Date: 5pm 22/7/24
Report author: Manisha Patel
Publication date: 15/07/2024
Date of decision: 15/07/2024
Decided at meeting: 15/07/2024 - Cabinet
Effective from: 23/07/2024