Issue - meetings

Oxford Street Programme – Oxford Street Scheme Stage 3

Meeting: 15/07/2024 - Cabinet (Item 4.)

4. Oxford Street Programme – Oxford Street Scheme Stage 3 pdf icon PDF 3 MB

To approve the development of a Stage 3 (detailed) design for the Oxford Street project.

Additional documents:

Decision:

Cabinet approved the option to proceed to Stage 3 design on the basis set out in the report in the knowledge that the remaining funding is yet to be formally confirmed.  

 

Cabinet also approved spend of £3.845m to progress the Stage 3 design.

 

Reasons for Decision: The Stage 2 design for Oxford Street is complete and the finalisation of design is required in advance of pre-mobilisation and construction. A decision is required on how to progress the Oxford Street project. 

 

Implementation Date: 5pm 22/7/24