Decision Maker: Cabinet Member for Finance and Council Reform
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Summary of Decision
To approve the variation to the contract for the delivery of the new extension and refurbishment of the Coroners Court with CBRE Managed Services Limited in terms of additional costs and time. The additional budget spend amounts to £907,020 excluding VAT (£1,088,422 including VAT
Reasons for Decision
As the project has progressed there have been some issues encountered which have resulted in CBRE seeking an Extension of Time (EOT).Utilising CBRE Managed Services for additional works whilst they are on-site provides greater value for money rather than progressing at a later date at a greater cost and avoids service disruption.
Publication date: 23/06/2023
Date of decision: 23/06/2023
Effective from: 01/07/2023
Accompanying Documents: