Oxford Street Programme - Oxford Street West Schemes

Decision Maker: Cabinet Member for Planning and Economic Development

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

Summary of Decision

The Cabinet Member for Planning and Economic Development has: 

1.     Approved the scope and proposals for the Oxford Street West Scheme area and the investment required to design the corresponding projects.

 

2.     Approved capital expenditure of £2.442m to progress the design for the items outlined in 1.2 above.

 

Reasons for Decision 

The projects proposed within the Oxford Street West Scheme area are being progressed as part of wider OSP initiatives and are complementary to the Oxford Street design. The interventions aim to reduce traffic reduction in Marylebone and Mayfair and enhance traffic resilience in the surrounding network through the introduction of right-hand turning movements at two junctions to the north of Oxford Street resulting in shorter vehicular journeys.

Expenditure is required to progress the design of the Oxford Street West projects to allow for their construction in 2025.

 

Publication date: 12/12/2023

Date of decision: 20/12/2023

Effective from: 30/12/2023

Accompanying Documents: