Ebury Estate Renewal - Revised Phasing Programme

This decision seeks the approval of a revised phasing programme for the Ebury Estate renewal project and to redirect the already approved expenditure of £8.9M for Phase 2A to the new Phase 2 as per the revised phasing programme.

 

Decision type: Key

Reason Key: Significant expenditure/savings;

Decision status: Recommendations Approved

Wards affected: Knightsbridge and Belgravia;

Notice of proposed decision first published: 15/07/2022

Decision due: 15 Aug 2022 by Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform

Lead director: Gerald Almeroth, Debbie Jackson

Contact: Vikki Everett, Head of Development Email: veverett@westminster.gov.uk.

Decisions

Documents